Our Time Schedule

The schedule in HIGH-M behaves parallel to the PhD-project taking place in it. The execution of the central study is planned within two years and consists of three single papers and several milestones over it's course. Along these milestones one can track the development and application of the new analysis system.


Time Schedule

Timespan Content Goal Status
until October 2023 Method Development finished
until January 2024 Method Optimisation finished
March 2024 Milestone 1: Manually applicable and automatable Analysis System finished
until March 2024 Finalisation of the Analysis Method finished
until June 2024 Implementation of automatic Segmentation finished
until July 2024 Submission of Research Paper I finished
from October 2024 Start of Data Collection at HfM Nürnberg finished
until November 2024 Implementation of automatic Annotation finished
until January 2025 Assessment of automated Analysis finished
January 2025 Milestone 2: Finished automated Analysis System finished
until March 2024 Finished Data Collection at HfM Nürnberg finished
March 2025 Milestone 3: Complete Improvisation Datasets from Nürnberg and Jyväskylä finished
March 2025 Submission of Research Paper II finished
April 2025 Preprocessing of empirical Data finished
until July 2025 Comparative Data Analysis finished
July 2025 Comparative Analysis of both Data Sets finished
until September 2025 Milestone 4: Submission Research Paper III finished